Files
metaverseDubai/MILESTONES.md

10 KiB

Milestones - Dubai Metaverse

Overview

This document tracks all project milestones, deliverables, and success criteria for the 90-day Dubai Metaverse production plan.

Milestone Summary

Milestone Target Date Phase Status
M1: Project Setup Day 7 Phase 1 Pending
M2: Blockout Complete Day 15 Phase 1 Pending
M3: Procedural Generation Day 22 Phase 2 Pending
M4: Hero Asset Complete Day 29 Phase 2 Pending
M5: Architecture Complete Day 36 Phase 2 Pending
M6: Lighting Complete Day 43 Phase 3 Pending
M7: Vehicles & Water Day 50 Phase 3 Pending
M8: NPCs Complete Day 57 Phase 3 Pending
M9: Interactions Complete Day 64 Phase 4 Pending
M10: Cinematic Complete Day 71 Phase 4 Pending
M11: Final Delivery Day 90 Phase 5 Pending

Status Legend:

  • Complete
  • 🟡 In Progress
  • Pending
  • Blocked

M1: Project Setup (Day 7)

Deliverables

  • Project charter and technical brief
  • Art bible and visual style guide
  • District selection (Dubai Marina + Cayan Tower)
  • Unreal Engine 5.4 project initialized
  • Version control configured (Git LFS)
  • Project folder structure created
  • Naming conventions established
  • Essential plugins installed

Success Criteria

  • All documentation complete and reviewed
  • UE5 project ready for asset import
  • Version control working correctly
  • Team can begin work immediately
  • No blocking issues

Checklist

  • README.md created
  • PROJECT_CHARTER.md created
  • TECHNICAL_BRIEF.md created
  • ART_BIBLE.md created
  • DISTRICT_SELECTION.md created
  • PROJECT_PLAN.md created
  • PIPELINE.md created
  • NAMING_CONVENTIONS.md created
  • UE5_SETUP.md created
  • PROJECT_SETTINGS.md created
  • PLUGINS.md created
  • VERSION_CONTROL.md created
  • MILESTONES.md created (this file)
  • .gitignore created
  • .gitattributes created
  • UE5 project created and configured
  • Git LFS initialized
  • Plugins installed and verified

M2: Blockout Complete (Day 15)

Deliverables

  • OpenStreetMap data imported
  • GIS/DEM terrain data processed
  • Playable graybox level
  • Accurate building footprints
  • Road network established
  • Asset list (Tier 1, 2, 3)
  • Blockout review completed

Success Criteria

  • Blockout accurately represents Dubai Marina
  • Scale is 1:1 and validated
  • Navigation flow is logical
  • Asset list is comprehensive
  • Layout approved by stakeholders

Checklist

  • OpenStreetMap data imported
  • Terrain generated from elevation data
  • Building footprints created
  • Road network established
  • Graybox level playable
  • Scale validated (1:1)
  • Navigation flow tested
  • Asset list created (Tier 1, 2, 3)
  • Blockout review completed
  • Stakeholder approval received

M3: Procedural Generation (Day 22)

Deliverables

  • PCG graphs for building placement
  • PCG graphs for road props
  • PCG graphs for vegetation
  • Houdini HDAs for building generation
  • Populated blockout (60-70% proxy buildings)
  • Procedural workflow documented

Success Criteria

  • Blockout fully populated procedurally
  • 60-70% of buildings represented
  • Procedural system is reusable
  • Performance is acceptable
  • Workflow is documented

Checklist

  • PCG building placement graph created
  • PCG road props graph created
  • PCG vegetation graph created
  • Houdini building generator HDA created
  • Blockout populated with procedural content
  • 60-70% buildings represented
  • Performance tested and acceptable
  • Procedural workflow documented
  • PCG graphs validated

M4: Hero Asset Complete (Day 29)

Deliverables

  • Cayan Tower high-poly model
  • 8K texture sets (UDIM workflow)
  • Nanite static mesh
  • PBR materials (glass, chrome, etc.)
  • Hero asset imported to UE5

Success Criteria

  • Hero asset is photoreal quality
  • 8K textures are properly applied
  • Nanite mesh renders correctly
  • Materials match reference
  • Visual quality meets standards

Checklist

  • Cayan Tower high-poly model complete
  • 8K texture sets created (UDIM)
  • Materials created (glass, chrome, etc.)
  • Nanite mesh imported to UE5
  • Materials assigned correctly
  • Visual quality validated
  • Performance tested
  • Reference comparison completed

M5: Architecture Complete (Day 36)

Deliverables

  • 20-40 primary buildings modeled
  • Dubai architecture material library
  • 4K texture sets for buildings
  • Shader variations (dust, fingerprints, weathering)
  • Global decal pass
  • 70-80% buildings at production detail

Success Criteria

  • 70-80% buildings complete
  • Material library is comprehensive
  • Textures are production quality
  • Performance is maintained
  • Visual consistency achieved

Checklist

  • 20-40 primary buildings modeled
  • Material library created
  • 4K textures applied
  • Shader variations created
  • Global decals applied
  • 70-80% buildings at production detail
  • Performance validated
  • Visual consistency checked

M6: Lighting Complete (Day 43)

Deliverables

  • HDRI sky setup
  • Day/night cycle system
  • Volumetric fog and atmosphere
  • Heat haze shader
  • Post-process volume
  • Sunrise to sunset cycle working

Success Criteria

  • Lighting matches Dubai aesthetic
  • Day/night cycle transitions smoothly
  • Performance is acceptable
  • Visual quality is cinematic
  • Atmosphere is realistic

Checklist

  • HDRI sky configured
  • Directional light with day/night cycle
  • Lumen GI and reflections working
  • Volumetric fog configured
  • Heat haze shader created
  • Post-process volume configured
  • Day/night cycle tested
  • Performance validated
  • Visual quality approved

M7: Vehicles & Water (Day 50)

Deliverables

  • Dubai supercars (Lamborghini, G-Wagon, Ferrari)
  • Chaos vehicle system working
  • Marina water shader with reflections
  • Particle effects (dust, heat, sand, fountains)
  • AI traffic spline system
  • Drivable vehicle

Success Criteria

  • Vehicles drive realistically
  • Water looks photoreal
  • Particle effects enhance atmosphere
  • Performance is maintained
  • All systems functional

Checklist

  • Supercar models imported/created
  • Chaos vehicle system configured
  • Vehicle controller working
  • Marina water shader created
  • Particle effects created
  • AI traffic system working
  • Vehicles drivable and tested
  • Water simulation validated
  • Performance tested

M8: NPCs Complete (Day 57)

Deliverables

  • 5-10 MetaHumans created
  • Animation sets (walking, sitting, phone, gestures)
  • Behavior trees for NPCs
  • NPC AI controller
  • ChatGPT integration (optional)
  • NPCs populating district

Success Criteria

  • NPCs look realistic
  • Behavior is natural
  • Performance is acceptable
  • Dialogue system works (if implemented)
  • District feels alive

Checklist

  • 5-10 MetaHumans created
  • Animations imported/created
  • Behavior trees created
  • NPC controller working
  • ChatGPT integration (optional)
  • NPCs placed in level
  • Behavior tested
  • Performance validated
  • Visual quality approved

M9: Interactions Complete (Day 64)

Deliverables

  • Player controller (first/third-person)
  • Interaction system framework
  • Interactable objects (doors, holograms, info panels, elevators)
  • UI widgets (main menu, mini-map, interaction prompts)
  • Teleport/fast travel system
  • Simple quest/navigation system

Success Criteria

  • All interactions work correctly
  • UI is functional and polished
  • Navigation is intuitive
  • Performance is maintained
  • User experience is smooth

Checklist

  • Player controller created
  • Interaction system implemented
  • Interactable objects working
  • UI widgets created
  • Teleport system working
  • Navigation system functional
  • All interactions tested
  • UI polished
  • Performance validated

M10: Cinematic Complete (Day 71)

Deliverables

  • 6-12 cinematic sequences
  • Master cinematic sequence
  • Movie Render Queue presets (8K EXR, 4K MP4)
  • Performance optimizations
  • LOD system complete
  • World Partition streaming optimized
  • 45-60 second 8K cinematic trailer

Success Criteria

  • Cinematic renders at 8K successfully
  • Playable demo runs at 60-90 FPS
  • All optimizations implemented
  • Visual quality maintained
  • Trailer is production-ready

Checklist

  • 6-12 cinematic sequences created
  • Master sequence assembled
  • MRQ presets configured
  • 8K EXR render successful
  • Performance optimizations complete
  • LOD system validated
  • Streaming optimized
  • 8K cinematic trailer rendered
  • Trailer reviewed and approved

M11: Final Delivery (Day 90)

Deliverables

  • Comprehensive testing completed
  • Audio integrated (ambient, vehicles, footsteps, music)
  • Final build packaged (Windows)
  • Pixel Streaming setup (optional)
  • VR stub (optional)
  • Complete documentation
  • Developer handoff kit

Success Criteria

  • All systems tested and working
  • Build packages successfully
  • Documentation is complete
  • Ready for delivery
  • Meets all quality standards

Checklist

  • Testing checklist completed
  • All bugs fixed
  • Audio integrated
  • Final game mode configured
  • Windows build packaged
  • Pixel Streaming setup (optional)
  • VR stub created (optional)
  • Documentation complete
  • Developer handoff kit prepared
  • Final review completed
  • Delivery approved

Progress Tracking

Weekly Reviews

  • Week 1: M1 status review
  • Week 2: M2 status review
  • Week 3: M3 status review
  • Week 4: M4 status review
  • Week 5: M5 status review
  • Week 6: M6 status review
  • Week 7: M7 status review
  • Week 8: M8 status review
  • Week 9: M9 status review
  • Week 10: M10 status review
  • Week 11-12: M11 status review

Risk Assessment

  • Green: On track, no issues
  • Yellow: Minor delays, manageable
  • Red: Significant delays, action required

Version: 1.0 Last Updated: [Current Date] Next Review: [Weekly]