# SMOA Project Completion Checklist
|
||
|
|
|
||
|
|
**Last Updated:** 2024-12-20
|
||
|
|
**Reference:** See `PROJECT_REVIEW.md` for detailed analysis
|
||
|
|
|
||
|
|
---
|
||
|
|
|
||
|
|
## Phase 1: Foundation Completion (Months 1-3)
|
||
|
|
|
||
|
|
### Month 1: Test Infrastructure & Critical Security
|
||
|
|
|
||
|
|
#### Week 1-2: Test Infrastructure
|
||
|
|
- [ ] Set up JUnit 5 and MockK
|
||
|
|
- [ ] Create test utilities and helpers
|
||
|
|
- [ ] Set up Compose UI testing
|
||
|
|
- [ ] Create mock implementations
|
||
|
|
- [ ] Write tests for core:auth (target 70% coverage)
|
||
|
|
- [ ] Write tests for core:security (target 70% coverage)
|
||
|
|
- [ ] Set up CI/CD test execution
|
||
|
|
- [ ] Configure coverage reporting
|
||
|
|
|
||
|
|
#### Week 3: Screenshot Prevention & VPN
|
||
|
|
- [ ] Implement FLAG_SECURE for credential screens
|
||
|
|
- [ ] Implement media projection detection
|
||
|
|
- [ ] Implement screen recording detection
|
||
|
|
- [ ] Create ScreenProtection utility
|
||
|
|
- [ ] Integrate VPN API
|
||
|
|
- [ ] Implement VPN connection monitoring
|
||
|
|
- [ ] Enforce VPN in browser module
|
||
|
|
- [ ] Test VPN integration
|
||
|
|
|
||
|
|
#### Week 4: Database Encryption & Dual Biometric
|
||
|
|
- [ ] Integrate SQLCipher
|
||
|
|
- [ ] Implement encrypted Room databases
|
||
|
|
- [ ] Bind database keys to auth state
|
||
|
|
- [ ] Implement separate fingerprint verification
|
||
|
|
- [ ] Implement separate facial recognition verification
|
||
|
|
- [ ] Update AuthCoordinator for sequential verification
|
||
|
|
- [ ] Test dual biometric flow
|
||
|
|
|
||
|
|
### Month 2: Core Functional Modules
|
||
|
|
|
||
|
|
#### Week 5-6: Directory Module
|
||
|
|
- [ ] Design directory database schema
|
||
|
|
- [ ] Implement DirectoryDao
|
||
|
|
- [ ] Implement DirectoryRepository
|
||
|
|
- [ ] Implement DirectoryService with search
|
||
|
|
- [ ] Implement role/unit scoping
|
||
|
|
- [ ] Implement offline cache
|
||
|
|
- [ ] Create DirectoryListScreen UI
|
||
|
|
- [ ] Create SearchScreen UI
|
||
|
|
- [ ] Create ContactDetailScreen UI
|
||
|
|
- [ ] Write unit tests
|
||
|
|
- [ ] Write UI tests
|
||
|
|
|
||
|
|
#### Week 7-8: Browser Module
|
||
|
|
- [ ] Implement BrowserService
|
||
|
|
- [ ] Implement URLFilter with allow-list
|
||
|
|
- [ ] Integrate WebView with restrictions
|
||
|
|
- [ ] Implement VPN requirement enforcement
|
||
|
|
- [ ] Implement certificate pinning
|
||
|
|
- [ ] Implement download controls
|
||
|
|
- [ ] Implement external app isolation
|
||
|
|
- [ ] Create BrowserScreen UI
|
||
|
|
- [ ] Create AllowListScreen UI
|
||
|
|
- [ ] Write unit tests
|
||
|
|
- [ ] Write UI tests
|
||
|
|
|
||
|
|
### Month 3: Communications & Meetings
|
||
|
|
|
||
|
|
#### Week 9-10: Communications Module
|
||
|
|
- [ ] Integrate WebRTC library
|
||
|
|
- [ ] Implement CommunicationsService
|
||
|
|
- [ ] Implement ChannelManager
|
||
|
|
- [ ] Implement VoiceTransport with encryption
|
||
|
|
- [ ] Implement PTT controls
|
||
|
|
- [ ] Implement channel authorization
|
||
|
|
- [ ] Create ChannelListScreen UI
|
||
|
|
- [ ] Create PTTScreen UI
|
||
|
|
- [ ] Implement session metadata logging
|
||
|
|
- [ ] Write unit tests
|
||
|
|
- [ ] Write UI tests
|
||
|
|
|
||
|
|
#### Week 11-12: Meetings Module
|
||
|
|
- [ ] Integrate WebRTC for video
|
||
|
|
- [ ] Implement MeetingsService
|
||
|
|
- [ ] Implement MeetingRoom management
|
||
|
|
- [ ] Implement ParticipantManager
|
||
|
|
- [ ] Implement screen sharing (policy-controlled)
|
||
|
|
- [ ] Implement file transfer (policy-controlled)
|
||
|
|
- [ ] Implement step-up authentication
|
||
|
|
- [ ] Create MeetingListScreen UI
|
||
|
|
- [ ] Create MeetingScreen UI
|
||
|
|
- [ ] Write unit tests
|
||
|
|
- [ ] Write UI tests
|
||
|
|
|
||
|
|
---
|
||
|
|
|
||
|
|
## Phase 2: Security & Integration (Months 4-6)
|
||
|
|
|
||
|
|
### Month 4: Cryptographic Implementations
|
||
|
|
|
||
|
|
#### Week 13-14: Digital Signatures
|
||
|
|
- [ ] Integrate BouncyCastle library
|
||
|
|
- [ ] Implement RSA signature generation
|
||
|
|
- [ ] Implement ECDSA signature generation
|
||
|
|
- [ ] Implement signature verification
|
||
|
|
- [ ] Implement certificate chain validation
|
||
|
|
- [ ] Update DigitalSignatureService
|
||
|
|
- [ ] Integrate with orders and evidence modules
|
||
|
|
- [ ] Write unit tests
|
||
|
|
|
||
|
|
#### Week 15-16: XML Security
|
||
|
|
- [ ] Integrate Apache Santuario
|
||
|
|
- [ ] Implement XMLDSig signing
|
||
|
|
- [ ] Implement XMLEnc encryption
|
||
|
|
- [ ] Implement canonicalization
|
||
|
|
- [ ] Create XMLSecurity utility
|
||
|
|
- [ ] Integrate with AS4 gateway
|
||
|
|
- [ ] Write unit tests
|
||
|
|
|
||
|
|
#### Week 17: Certificate Revocation
|
||
|
|
- [ ] Implement OCSP client
|
||
|
|
- [ ] Implement CRL download and parsing
|
||
|
|
- [ ] Implement revocation checking workflow
|
||
|
|
- [ ] Implement cache management
|
||
|
|
- [ ] Update CertificateManager
|
||
|
|
- [ ] Write unit tests
|
||
|
|
|
||
|
|
### Month 5: AS4 Gateway
|
||
|
|
|
||
|
|
#### Week 18-19: AS4 Core Implementation
|
||
|
|
- [ ] Integrate Apache CXF
|
||
|
|
- [ ] Implement SOAP envelope construction
|
||
|
|
- [ ] Implement AS4 message builder
|
||
|
|
- [ ] Implement party management
|
||
|
|
- [ ] Update AS4Service
|
||
|
|
- [ ] Write unit tests
|
||
|
|
|
||
|
|
#### Week 20-21: AS4 Security & Reliability
|
||
|
|
- [ ] Implement WS-Security headers
|
||
|
|
- [ ] Integrate XMLDSig for AS4
|
||
|
|
- [ ] Integrate XMLEnc for AS4
|
||
|
|
- [ ] Implement WS-ReliableMessaging
|
||
|
|
- [ ] Implement receipt generation
|
||
|
|
- [ ] Implement error signal handling
|
||
|
|
- [ ] Write unit tests
|
||
|
|
|
||
|
|
#### Week 22: AS4 Pull Protocol
|
||
|
|
- [ ] Implement pull protocol
|
||
|
|
- [ ] Implement message polling
|
||
|
|
- [ ] Implement MPC support
|
||
|
|
- [ ] Implement CPA management
|
||
|
|
- [ ] Write integration tests
|
||
|
|
|
||
|
|
### Month 6: Offline Sync & UI Enhancements
|
||
|
|
|
||
|
|
#### Week 23-24: Offline Synchronization
|
||
|
|
- [ ] Implement SyncService
|
||
|
|
- [ ] Implement conflict resolution
|
||
|
|
- [ ] Implement sync queue management
|
||
|
|
- [ ] Implement offline duration monitoring
|
||
|
|
- [ ] Implement data integrity checking
|
||
|
|
- [ ] Implement automatic purge
|
||
|
|
- [ ] Create OfflinePolicyManager
|
||
|
|
- [ ] Integrate with all modules
|
||
|
|
- [ ] Write unit tests
|
||
|
|
- [ ] Write integration tests
|
||
|
|
|
||
|
|
#### Week 25-26: UI/UX Enhancements
|
||
|
|
- [ ] Implement foldable UI variants
|
||
|
|
- [ ] Create dual-pane layouts
|
||
|
|
- [ ] Create compact layouts
|
||
|
|
- [ ] Implement anti-spoofing overlays
|
||
|
|
- [ ] Implement time markers
|
||
|
|
- [ ] Enhance credential display
|
||
|
|
- [ ] Improve navigation
|
||
|
|
- [ ] Write UI tests
|
||
|
|
|
||
|
|
---
|
||
|
|
|
||
|
|
## Phase 3: Domain-Specific & Advanced (Months 7-12)
|
||
|
|
|
||
|
|
### Month 7-8: Domain Module Completion
|
||
|
|
|
||
|
|
#### Week 27-28: ATF Module
|
||
|
|
- [ ] Complete ATF UI implementations
|
||
|
|
- [ ] Implement form workflows
|
||
|
|
- [ ] Implement validation
|
||
|
|
- [ ] Implement submission (when API available)
|
||
|
|
- [ ] Write tests
|
||
|
|
|
||
|
|
#### Week 29-30: NCIC Module
|
||
|
|
- [ ] Complete NCIC UI implementations
|
||
|
|
- [ ] Implement query builder UI
|
||
|
|
- [ ] Implement response display
|
||
|
|
- [ ] Implement ORI/UCN management UI
|
||
|
|
- [ ] Write tests
|
||
|
|
|
||
|
|
#### Week 31-32: Military, Judicial, Intelligence Modules
|
||
|
|
- [ ] Complete Military module UI
|
||
|
|
- [ ] Complete Judicial module workflows
|
||
|
|
- [ ] Complete Intelligence MLS system
|
||
|
|
- [ ] Implement compartment UI
|
||
|
|
- [ ] Write tests
|
||
|
|
|
||
|
|
### Month 9-10: External Integrations (Pending Approvals)
|
||
|
|
|
||
|
|
#### Week 33-36: eIDAS QTSP Integration
|
||
|
|
- [ ] Select QTSP provider
|
||
|
|
- [ ] Obtain API access
|
||
|
|
- [ ] Implement QTSP client
|
||
|
|
- [ ] Implement qualified signature workflow
|
||
|
|
- [ ] Implement trust list validation
|
||
|
|
- [ ] Integrate TSA for timestamps
|
||
|
|
- [ ] Write tests
|
||
|
|
|
||
|
|
#### Week 37-40: NCIC/III API Integration
|
||
|
|
- [ ] Complete CJIS approval process
|
||
|
|
- [ ] Obtain API credentials
|
||
|
|
- [ ] Implement NCIC API client
|
||
|
|
- [ ] Implement CJIS authentication
|
||
|
|
- [ ] Implement query execution
|
||
|
|
- [ ] Implement response parsing
|
||
|
|
- [ ] Write tests
|
||
|
|
|
||
|
|
#### Week 41-44: ATF eTrace Integration
|
||
|
|
- [ ] Complete federal approval process
|
||
|
|
- [ ] Obtain API access
|
||
|
|
- [ ] Implement eTrace API client
|
||
|
|
- [ ] Implement form submission
|
||
|
|
- [ ] Implement trace queries
|
||
|
|
- [ ] Write tests
|
||
|
|
|
||
|
|
### Month 11-12: Advanced Features & Optimization
|
||
|
|
|
||
|
|
#### Week 45-46: Threat Detection
|
||
|
|
- [ ] Implement behavioral anomaly detection
|
||
|
|
- [ ] Implement security event correlation
|
||
|
|
- [ ] Implement threat scoring
|
||
|
|
- [ ] Implement automated response
|
||
|
|
- [ ] Update ThreatDetection
|
||
|
|
- [ ] Write tests
|
||
|
|
|
||
|
|
#### Week 47-48: Performance Optimization
|
||
|
|
- [ ] Database query optimization
|
||
|
|
- [ ] UI performance tuning
|
||
|
|
- [ ] Memory management improvements
|
||
|
|
- [ ] Battery optimization
|
||
|
|
- [ ] Performance testing
|
||
|
|
|
||
|
|
#### Week 49-52: Final Integration & Testing
|
||
|
|
- [ ] End-to-end testing
|
||
|
|
- [ ] Security testing
|
||
|
|
- [ ] Performance testing
|
||
|
|
- [ ] User acceptance testing
|
||
|
|
- [ ] Bug fixes
|
||
|
|
- [ ] Documentation completion
|
||
|
|
|
||
|
|
---
|
||
|
|
|
||
|
|
## Phase 4: Certification & Deployment (Months 13-24)
|
||
|
|
|
||
|
|
### Months 13-18: Security Testing & Compliance
|
||
|
|
- [ ] Penetration testing
|
||
|
|
- [ ] Security audit
|
||
|
|
- [ ] Compliance validation
|
||
|
|
- [ ] Documentation review
|
||
|
|
- [ ] Remediation
|
||
|
|
|
||
|
|
### Months 19-24: ATO Process
|
||
|
|
- [ ] ATO package preparation
|
||
|
|
- [ ] Security Control Assessment (SCA)
|
||
|
|
- [ ] Risk assessment
|
||
|
|
- [ ] Documentation finalization
|
||
|
|
- [ ] Authorization decision
|
||
|
|
|
||
|
|
---
|
||
|
|
|
||
|
|
## Critical Dependencies & Approvals
|
||
|
|
|
||
|
|
### External Approvals Required
|
||
|
|
- [ ] **CJIS Approval** for NCIC/III (Start early - 3-6 months)
|
||
|
|
- [ ] **Federal Approval** for ATF eTrace (Start early - 2-4 months)
|
||
|
|
- [ ] **QTSP Provider Selection** for eIDAS (Start early - 1-2 months)
|
||
|
|
|
||
|
|
### Library Integrations
|
||
|
|
- [ ] Apache CXF for AS4
|
||
|
|
- [ ] BouncyCastle for cryptography
|
||
|
|
- [ ] Apache Santuario for XML security
|
||
|
|
- [ ] WebRTC for communications/meetings
|
||
|
|
- [ ] SQLCipher for database encryption
|
||
|
|
|
||
|
|
---
|
||
|
|
|
||
|
|
## Quality Gates
|
||
|
|
|
||
|
|
### Phase 1 Gate (Month 3)
|
||
|
|
- [ ] Test coverage > 60%
|
||
|
|
- [ ] All core modules functional
|
||
|
|
- [ ] Critical security features implemented
|
||
|
|
- [ ] Zero high/critical vulnerabilities
|
||
|
|
|
||
|
|
### Phase 2 Gate (Month 6)
|
||
|
|
- [ ] Test coverage > 70%
|
||
|
|
- [ ] Complete security architecture
|
||
|
|
- [ ] AS4 gateway functional
|
||
|
|
- [ ] Offline sync operational
|
||
|
|
|
||
|
|
### Phase 3 Gate (Month 12)
|
||
|
|
- [ ] Test coverage > 80% (core), > 70% (features)
|
||
|
|
- [ ] All modules complete
|
||
|
|
- [ ] External integrations functional (where approved)
|
||
|
|
- [ ] Performance targets met
|
||
|
|
|
||
|
|
### Phase 4 Gate (Month 24)
|
||
|
|
- [ ] Security testing passed
|
||
|
|
- [ ] Compliance validated
|
||
|
|
- [ ] ATO obtained
|
||
|
|
- [ ] Production ready
|
||
|
|
|
||
|
|
---
|
||
|
|
|
||
|
|
## Notes
|
||
|
|
|
||
|
|
- Check off items as completed
|
||
|
|
- Update dates when milestones are reached
|
||
|
|
- Add notes for blockers or issues
|
||
|
|
- Review weekly with team
|
||
|
|
- Update this checklist as priorities change
|
||
|
|
|
||
|
|
---
|
||
|
|
|
||
|
|
**Last Review Date:** _______________
|
||
|
|
**Next Review Date:** _______________
|
||
|
|
**Status:** _______________
|
||
|
|
|